Water Board Update 1-24-19

PROJECT UPDATE 1-24-2019

 

 

Existing Basins Demolition

Demolition of the Existing Basins is expected to begin as early as next week (January 28th). There will be a strict dust mitigation plan in place and we will be monitoring noise and vibration to minimize as much disruption as possible. Please note, there will be no demolition work outside of normal hours (Monday – Friday from 7:30am to 4:30pm).

 

Stockpile

Work on the backfill of the new tanks continues. Due to the time of year and the possibility of inclement weather conditions, we anticipate the large stockpile along Happy Canyon Road to be gone by the end of March 2019. There will be increased truck traffic in mid-February as we start the backfill behind the retaining wall.

 

General Construction Hours

General work hours are 7:00 a.m. – 6:00 p.m. Monday – Friday.

 

Saturday work will continue to be an option the contractor and MWHC will retain and use when necessary to keep the project on schedule or at times when the additional work could result in condensing the overall construction timeline. Saturday work hours will be consistent with weekday hours 7:00 a.m. – 6:00 p.m.

 

Questions? Please contact:

 

Julie Seagren                                 Casey Corrigan

Denver Water                                 MWH Constructors

julie.seagren@denverwater.org     casey.corrigan@stantec.com

303-628-6421                                303-410-4174

 

 

 

 

 

Board Meeting – January 2019

ATTENTION RESIDENTS!

Tuesday, January 15th, 2019

We will be having our next Board Meeting at 6:30 pm in the Clubhouse.

All residents are welcome and the Board appreciates feedback and ideas from our residents.

We look forward to seeing “You” at the meeting!