Hillcrest Project Update

 

Project Update 08-11-2021

Pump station

The new pump station is on track to be completed in late summer/early fall, at which point Denver Water will launch a testing phase. Testing should be completed by the end of the year. Demolition of the old pump station will follow the testing phase.

Landscaping

To ensure the new seeding and sod grew properly, we watered more than normal at the site. The native grass had its first cut last week, and watering has been reduced.

Road sweeping

We have reduced the street sweeping on Happy Canyon Road to two times per week. We will continue to sweep on additional days as needed.

Work hours

When Saturday work is required, we will continue to use our weekend schedule, with personnel arriving at 7 a.m. and work starting at 8 a.m. We do not anticipate working on Sundays for the foreseeable future. Weekday work hours will continue to be 7 a.m. to 6 p.m.

 

 

Questions? Please contact:

Amber Creasey

PR and Communications

MWH Constructors, Inc.

amber.creasey@mwhconstructors.com

720-547-5451

 

Gianna Lombardi

Denver Water

gianna.lombardi@denverwater.org

303-634-3724